Riot Names Anthropic as Tenant in $28 Billion Texas Lease

The bitcoin miner says Anthropic could receive rent credits carrying 12% annual interest if Riot cannot secure acceptable financing for construction costs.

Riot Names Anthropic as Tenant in $28 Billion Texas Lease Craftsman Concrete Floors

Riot Platforms has identified Anthropic as the tenant behind a 15-year lease for its Corsicana, Texas, campus, disclosing the name in a quarterly filing Wednesday. The deal is valued at about $28 billion and covers 910 megawatts of critical IT capacity.

The lease also contains a financing provision that could leave Riot granting Anthropic rent credits with 12% annual interest. That outcome depends on Riot being unable to raise money on market terms it finds reasonably acceptable for reimbursing the tenant’s data center module costs.

Riot signed the lease through a subsidiary on Oct. 28, and it became binding Nov. 4 after board approval and consultant review of technical specifications, according to the filing. The disclosure also identifies Anthropic as the tenant under a separate 191 MW Rockdale lease signed in August, bringing its contracted capacity with Riot to 1,101 MW. AMD holds the remaining 50 MW of Riot’s 1,151 MW in contracted capacity.

How the 12% provision works

Riot agreed to reimburse Anthropic up to $4 million per megawatt for modules installed by the tenant, or about $3.6 billion across the full Corsicana capacity. If Riot cannot obtain financing on acceptable market terms, it will instead provide rent credits that amortize the amount plus 12% annual interest over the rest of the initial lease term.

Riot says it expects to fund reimbursements with non-recourse project debt sized to the contracted rent. It estimates total capital needs at about $5.5 billion, or $6 million per megawatt, and said it does not currently expect to issue equity for the project. The filing does not say that the 12% rent-credit option will be used.

Delivery schedule and Riot’s bitcoin sales

Riot plans to deliver capacity in three phases: 400 MW, with the first block targeted for June 28, 2027; 200 MW beginning Dec. 24, 2027; and 310 MW on July 30, 2028. Delays beyond 60 days trigger escalating rent credits, while a phase delayed more than 270 days beyond its target can be terminated by Anthropic on 30 days’ notice, subject to force majeure extensions.

The build is also reshaping Riot’s bitcoin holdings. The company sold 20,264 BTC for about $1.5 billion in the first nine months of 2026 and ended September with 2,418 BTC worth $202 million. Riot said it expects to continue selling substantially all of the bitcoin it mines and does not expect significant holdings in the near term.

This report draws on information from Bitcoin Magazine.

Editorial checks passed Facts, figures and quotes checked against 1 source

Bitcoin Mining and Solar Power Landscapes in Pictures In pictures · 12 photosBitcoin Mining and Solar Power Landscapes in Pictures

Add Cryptos News as a preferred source on Google